Please answer?
Question:
Answer:
a. CPI <1>
b. CPI > 1
c. CPI <0>
d. SPI = 1
2.Diane was so concered about her project that she woke up dreaming about it. She thought to herself, "Well, our EV is 2, our AC is 4 and our PV is 6 so that means
Answer:
a. our productivity was less than planned
b. our cost variance is negative
c. our cost estimate at completion is 6
d. a, c, and d
e. our CPI and SPI are both positive
3.There are usually two types of reserves in a project's budget. The _____ reserve is for cost variances from the plan because of inaccurate estimates or pricing and costs overruns, while the ____ is to accommodate costs for project work that were not included in the plan through error or oversight.
Answer:
a. engineering; management allowance
b. management; contingency allowance
c. project; budget overrun allowance
d. management; mismanagement allowance
Answer:
question #3 the "B" management contingency allowance
and "C" project budget overrun allowance
Sorry the first two questions I can't understand the CPI, SPI etc, I am in Canada and I think we use different terminologies for them EV AC etc. if you can add the details, using the words instead of letters I can answer the questions for you.